Wednesday, March 14, 2007

Sand Update

Hi All - This is an update from Ray Newby, at the Texas General Land Office, to Tom:

The current status of the WGI repairs is that Shiner Moseley is working on the amendment items for the WGI Beach Nourishment permit from the Corps ofEngineers to add additional sand sources available to the project. The most significant source is the South Jetty Sand Source that may hold enough volume to meet our short and medium term sand needs. We're still shooting for the next construction window next Oct. through March after turtlenesting season ends. Please let me know if you need any additional info on this.
Ray Newby, P.G.Geomorphologist/Project Manager
Texas General Land OfficeCoastal Resources Program
ph. (512) 475-3624, fx (512) 475-0680

So we have been delayed until, the earliest, October ... which means we willgo through this hurricane season without the sand placement. Sorry wedidn't have better news!

Sunday, March 04, 2007

Meeting-3/3/7

Thanks to the Byerly's for hosting the March meeting for the Sunny Beach Neighborhood Association. Thanks to everyone who participated in the meeting. Next time we will have to check Eric Clapton's schedule before planning our meeting. :)

Testing 1234

Saturday, March 03, 2007

Neighborhood Meeting Tonight !!!! 3/3/2007

If your logging on to check the meeting status... It's Tonight at 5:30 at the Byerly's Home 11205 Bernice. Bring Yourselves, a light agenda follows but an important one as always. T.